Daisy Guyton Construction update!

Dates 2/29/06 - 3/01/06

WORK ACCOMPLISHED:
Finished framing some closets. Finished greenboarding bathroom. Finished drywalling a bedroom and started taping the seams. Started building kitchen island. Started drywalling main wall. Finished dry walling the living room, family room, main bedroom, hall closet and started the dining room.

The hole through the floor in the 1/2 bathroom, has been repaired and the hot water heater has been put in its place. The removable plywood panel above electric panel has been installed and all left over materials from previous crew were back to the tool shed.

WORK TO BE DONE:
drywalling main rooms and 2 bedrooms. hot water tank Mudding and putting up dry wall. Finish the last bedroom, laundry room, and dinning room, and mud and sand all rooms. Install hot water heater, and install side door.

MATERIALS NEEDED:
none listed